 |
 |
|
 |
WATER
TANK/RESERVOIR CONSTRUCTION

- INTRODUCTION
- A BRIEF OVERVIEW OF LAYERED SYSTEM
- COMMONLY ASKED QUESTIONS
- ANSWERS
INTRODUCTION
Typically concrete water tanks are manufactured
using moulds or mortar applied in layers over a temporary
base panel – In Australia the latter is by far the
most popular.
A BRIEF OVERVIEW OF LAYERED SYSTEM
- Set up base mould and introduce rebar
- Pour concrete base
- Set up frame (usually tubular steel) aligned with outside
of base
- Set up timber or steel panels to frame
- Apply steel mesh and wire to panels
- Apply first layer of mortar
- When mortar has set (say 12 hours) remove panels and
frame
- Continue to apply layers – in/outside
- Similar process for roof - All layer applications typically
shotcrete sprayed
COMMONLY ASKED QUESTIONS
- Why place the roof before spraying the in/outside Coats?
- It is claimed that spraying time is 1.5 hours –
could this be broken up into the various areas and times?
- How and why do you use steel fibres?
- What are the cost savings in materials through spraying?
- What other benefits are to be expected through spraying?
- What other applications can our spray equipment handle?
- How difficult is it to train operators and maintain
quality?
Note: All following values relate to a typical 5000 GAL
– 23000 LTR tank.
ANSWERS
- It is proven that by placing the roof before spraying
inside and outside coats the moisture liberated by the
inside coat within the tank hydrates the cements and helps
to “feed” the outside coat – through
the wire coat. This overcomes the problem or shrinkage
cracking, thus less leaks and just as importantly minimises
stresses within the structure that could develop into
leaks or failure at a later time. Following this procedure,
advantages are even more apparent when A/ Only “fatty:
sands are locally available B/ Very low local humidity
C/ Hot dry winds are prevalent.
- On a 5000 gallon, 23000 Ltr tank the typical application
times are:
Wire Coat 20 minutes
Roof 20 minutes
Inside & Fillett 15 minutes
Outside 10 minutes
TOTAL 65 minutes
Allowing sufficient time for moving from one job to the
next, 1.5 hours is in fact quite liberal.
- Normal mortars generally have quite adequate compressive
strength but minimal tensile strength. Steel fibres added
to the mix impart a significant tensile and flexural strength
to the mix; thus there is less need for use of mesh or
netting.
The most acceptable procedure is to bind the “build”
with plain wire in the normal manner, spray the “wire
coat” using a steel fibre mix. The roof inside and
outside coats use a normal mix. Subject to STRICT ADHERENCE
TO ENGINEERING DESIGN it is also possible to omit the
binding wire and use steel fibre mixes only.
- Since sprayed concrete is much denser than hand applied
or poured concrete, less material may be used with equal
or better results.
Note: - Spraying significantly reduces the air entrained
in the mix, plus it gives a better mechanical bond.
Typical volumes of material –
Wire Coat 13 cub ft 368 L
Inside Coat 10 cub ft 283 L
Roof Coat 14 cub ft 396 L
Outside finish 10 cub ft 283 L
Fillet 9 cub ft 255 L
Total volume not including Base, 56 cub ft (1585 L) say
2 cubic yards (1.6 Cubic Metres).
The above table applies to the typical water tank using
a sand to cement ratio of 3 to 1. These volumes may be
compared most favourably with the volumes required by
the use of other methods of application. Other cost savings
may be calculated by the deduction of cost of mesh and
its application time, should steel fibres be employed
on the “wire coat”.
- Further cost savings may be enjoyed by the complete
elimination of the “build”. Since spraying
does not require a rigid structure, it is quite feasible
to employ the following method.
- Pour and screed off base.
- Place heavy mesh, F72 etc into the concrete and
around the outer edge of the base – standing
upright to form the basic tank shape
- When initial or final set is complete and therefore
the mesh is standing solid –tie wire the ends
of the mesh
- Apply hessian or shadecloth etc wrapping around
the F72.
- Apply a spray coat to inside of build
- When initial set complete, remove wrapping
- Finish off in the previously described manner (2,
3)
A variation of the above procedure would be to use a much
lighter mesh than F72 but to “bind” in the
normal manner after removal of wrapping. One particular
advantage is that any size tank may be built without the
need for expensive and heavy moulds.
WARNING: - Since tanks above 136,000 litres generally
require that the wall be sealed but free to move radially
relative to the base, it is strongly advised that RELIABLE
ENGINEERING ADVICE BE SOUGHT BEFOREHAND.
Note: - Whilst the above procedure was developed by this
company in 1983 and has been promoted since without patent
cover or royalty claim, all intending users may feel free
to use the system without charge by this company.
- Most first time buyers have their equipment commissioned
by someone from within our company. This generally takes
about 4-6 hours when mixing pumping and spray techniques
are addressed as also equipment lubrication and maintenance.
After commissioning most operators build up their techniques
and confidence to the point where they “throw away
the trowel” after about a week.
|
|
 |
|
 |
 |
Copyright ©2003 Westend Industries
Pty Ltd.
Web Design by: Abacus
Design
|
|
 |
 |